Ship ScholarPASS 2.0 to all partner institutes by end of Q2 2026.
Progress
71%
34/48 tasks
Timeline
Feb 15, 2026 → Jun 30, 2026
95 working days · 1280 hrs
Budget
$178,400
of $240,000 estimated
Workforce
12 humans 5 agents
Manager: Faisal Khan
| Task | Status | Assignee | Due | Hrs |
|---|---|---|---|---|
| Build TPM module UI high | In Progress | Faisal Khan | May 22, 2026 | 4/16 |
| Wire AWP agent identity into TPM assignment high | Open | Faisal Khan | May 30, 2026 | 0/12 |
| Migrate partner data from ScholarPASS 1.x high | Completed | Daniel Cole | Apr 15, 2026 | 96/80 |
Partner training — wave 1
Live training for first 20 partner institute admins.
TPM module is the last major piece — kicking off this week.
Faisal Khan · May 15, 2026
Faisal Khan
Project Owner · 30%
Aisha Rahman
Contributor · 80%
Penny — Project Planner
Planner · gpt-5
ScholarPASS_2.0_GoLive_Runbook.md
Runbook
Architecture_Diagram.png
Architecture